Bethesda Bungalows' Blog

Green Building

Tag >> Kevin Gallagher

Happy Friday everyone, it's a beautiful spring morning here in the nation's capitol, and my taxes are done. The NIST Net Zero site is fully prepped and the basement has been dug to grade. The last load of stone for the stabilized construction entrance is in place, and assuming the rain isn't too heavy tomorrow, we should be ready to pour footers early next week. We've noticed that the soil drains and dries quite rapidly, a good sign.

Todd Cirner of Therrien Waddell has been working non-stop on getting our submittals over to the team at Jacobs Engineering for initial review, before they pass them onto Building Science Corp for final review. The requirements for this project have made the submittal process a bit more challenging than we are all used to, but we'll work through it.

 

Click here to continue reading the Bethesda Bungalows' blog.